The Planning & Scheduling Professional (PSP) Exam certification process involves passing an extensive exam that covers topics such as project planning and scheduling, resource allocation, resource leveling, progress monitoring, and project reporting. Planning & Scheduling Professional (PSP) Exam certification is an internationally recognized credential that can be applied to a number of different industries including construction, engineering, manufacturing, and IT. Candidates who earn the AACE-PSP certification have the opportunity to advance their careers and demonstrate their expertise in project management.


Earning the AACE-PSP certification demonstrates a professional's commitment to their career and their ability to perform at a high level in their field. Planning & Scheduling Professional (PSP) Exam certification allows professionals to showcase their expertise and enhances their credibility with employers, clients, and colleagues. The AACE-PSP certification also provides opportunities for career advancement, higher salaries, and increased job security.

 

NEW QUESTION # 61
What is the remaining work duration of Active D?

  • A. 4.
  • B. 8.
  • C. 3.
  • D. 0

Answer: A


NEW QUESTION # 62
Is activity 7001 pictured correctly in the precedence diagram?

  • A. Yes, except the early finish date is not shown.
  • B. Yes, the duration is 48 days.
  • C. No, the total float is not shown correctly.
  • D. No, the start-to-start and finish-to-finish relationships are backwards.

Answer: B


NEW QUESTION # 63
Which of the following are NOT normally included in the project scope statement, either directly or by reference?

  • A. Project deliverables
  • B. Project justification
  • C. Project objectives in terms of cost, schedule and quality measures
  • D. Project contract between the contractor and owner

Answer: B


NEW QUESTION # 64
Using the "normal" schedule, theoretically construct a hammock for activities 2001 through 2004. What is the duration of the hammock?

  • A. 91 days
  • B. 193 days
  • C. 168 days
  • D. 183 days

Answer: D


NEW QUESTION # 65
Using the "crashed" schedule, if you start Activity 2002 on August 12, 2001, what is the finish date for Activity 2002?

  • A. 09-18-01.
  • B. 09-15-01.
  • C. 09-08-01.
  • D. 09-28-01.

Answer: C


NEW QUESTION # 66
Midway through the project you received an executed change order for this project, adding thirty-three days to the contract for weather delays. In its simplest form, how would your next project update display the changed condition?

  • A. After Activity 1000, add a new Activity 1050 with a start-to-start relationship to Activity 1000, and tie the end of this new activity with a finish-to-finish relationship to the final activity of the project.
  • B. After Activity 1000, add a new Activity 1010 with a finish-to-start relationship to Activity 1000, and tie the end of this new activity with a finish-to-start relationship to the final activity of the project.
  • C. After Activity 1001, add a new Activity 1011 with a finish-to-start relationship to Activity 1000, and tie the end of this new activity with a finish-to-start relationship to the final activity of the project.

Answer: C


NEW QUESTION # 67
What is the actual duration as of the status date or data date of Activity B?

  • A. 7.
  • B. 0.
  • C. 4.
  • D. 3.

Answer: D


NEW QUESTION # 68
Activity durations are normally estimated in an intuitive and subjective way. All of the following will improve duration accuracy EXCEPT

  • A. Use gross building square footages. The pluses and minuses all average out.
  • B. Divide activities into smaller activities. This will increase activity detail and duration estimate accuracy.
  • C. Look at each activity independently and don't follow specific logic paths when assigning activity durations.
  • D. Use the people responsible for performing the work as a resource to assign activity durations.

Answer: A


NEW QUESTION # 69
In order for a claimant to be entitled to an extension of contract time for a delay event (and further to be considered compensable):

  • A. The delay must affect the contractor's planned construction schedule.
  • B. The delay must not cause monetary harm to the defendant.
  • C. The delay must be concurrent with the delay attributable to both parties.
  • D. The delay must affect the critical path.

Answer: D


NEW QUESTION # 70
Using the "normal" schedule, and assuming you are billing on the last day of the month for previous month and for appropriate partial months, how many invoices will you have for this project?

  • A. 36.
  • B. 42.
  • C. 40.
  • D. 37.

Answer: A


NEW QUESTION # 71
Activity 1001 started on the scheduled date but has slipped 10 days. Activity 10002 will slip 35 days. All remaining activities retain their original duration. What is the revised completion date?

  • A. 03-20-04
  • B. 03-11-04
  • C. 02-19-04
  • D. 03-21-04

Answer: B


NEW QUESTION # 72
What method would be the best way to determine the most likely as-built critical path of a project that is underway, and the schedule of which has been partially progressed?

  • A. Use the forward-looking critical path of the most current updates.
  • B. Use the progressed portion of the critical path of the baseline schedule.
  • C. Interview the project personnel for their perceptions and opinions because the schedule is usually inadequate.
  • D. Use the progressed portion of the critical path of all the updates previous to the current update.

Answer: A


NEW QUESTION # 73
During proofing of the product manual, a problem was discovered requiring 15 days additional time to effect a correction. How can the date of availability be maintained?

  • A. Delay manufacturing by 5 days.
  • B. Delay product release by 5 days.
  • C. Expedite printing by 5 days.
  • D. Expedite packaging by 5 days.

Answer: B


NEW QUESTION # 74
Using the "normal" schedule, if you start Activity 7001 on April 1, 2002, and using a 5-day workweek, what the finish date for Activity 7001?

  • A. 06-18-02.
  • B. 06-05-02.
  • C. 06-04-02.
  • D. 06-11-02.

Answer: B


NEW QUESTION # 75
Project schedules help control all of the following EXCEPT for_____________________.

  • A. Cost
  • B. Time
  • C. Resources
  • D. Quality

Answer: D


NEW QUESTION # 76
If no time extensions are granted and all actual delays are as described above, what will the total float calculation be at the end of the project?

  • A. 10 calendar days.
  • B. -14 calendar days.
  • C. 0 calendar days.
  • D. -20 calendar days.

Answer: B


NEW QUESTION # 77
Which of the following project planning situations is the most frequent contributor to cost overruns?

  • A. Inappropriate definition of work breakdown structure
  • B. lack of detailed planning for operational start-up
  • C. Inadequate definition of scope at the estimate (budget) stage
  • D. Insufficient planning for change management

Answer: C


NEW QUESTION # 78
Using the "normal" schedule, theoretically construct a hammock for activities 6001-6003. What is the duration of the hammock?

  • A. 267 days
  • B. 362 days
  • C. 255 days
  • D. 407 days

Answer: D


NEW QUESTION # 79
At a minimum, periodic reporting must be done at what interval?

  • A. As requested by the owner.
  • B. Monthly.
  • C. As requested by the project manager.
  • D. As specified in the contract documents.

Answer: D


NEW QUESTION # 80
Total float is defined as the amount of time an activity can be delayed without impacting

  • A. The end of that activity
  • B. The next activity
  • C. The overall project completion
  • D. The buoyancy of a successor activity

Answer: C


NEW QUESTION # 81
......