NEW QUESTION 12
Which of the following apply to dynamic item processor (DIP)? Note: There are 3 correct Answers to this question.

  • A. DIP is used to create a quotation.
  • B. Material determination is mandatory.
  • C. Usage of cost elements is mandatory.
  • D. Sources can be based on line items.
  • E. Sales prices are maintained in the DIP profile.

Answer: A,D,E

 

NEW QUESTION 13
A customer needs to analyse the capacity requirements of their network activities. Which reports do you recommend? Note: There are 2 correct Answers to this question.

  • A. Cost element reports
  • B. Hierarchical reports
  • C. Resource reports
  • D. Structure information system reports

Answer: D

 

NEW QUESTION 14
You used reductions to reduce the scheduled duration of all internally-processed activities in your project. However, the duration did not changed after overall network scheduling.
What do you check? Note: There are 2 correct Answers to this question.

  • A. If the reduction strategy is set in the network header
  • B. If the appropriate reduction type is set in the parameters for network scheduling
  • C. If the maximum reduction level is less than 100
  • D. If the reduction strategy is set in each activity

Answer: A,B

 

NEW QUESTION 15
You want to create a reservation for a material component assigned to a network activity. However, after releasing and saving the activity, no reservation is created. What are some possible reasons for the missing reservation? Note: There are 2 correct Answers to this question.

  • A. The availability check for material components indicates missing parts.
  • B. The material master is set to external procurement.
  • C. The material is assigned to the activity as a non-stock material.
  • D. The indicator Reservation/Purchase Requisition indicator for the material component assigned to the activity is set to "never".

Answer: A,D

 

NEW QUESTION 16
Which statement is valid regarding networks? Note: There are 2 correct Answers to this question.

  • A. Relationships can be used to connect activities of different networks.
  • B. A network can be activity-account-assigned and header-account-assigned.
  • C. A network activity can be assigned to several WBS elements.
  • D. Material components can be assigned to activity elements.

Answer: A,B

 

NEW QUESTION 17
How can you update the degree of processing for an activity?

  • A. By scheduling the activity
  • B. By changing the activity
  • C. By confirming the activity
  • D. By using results analysis

Answer: C

 

NEW QUESTION 18
You want to use subnetworks during the project. Which of the following statements describes subnetworks?

  • A. Subnetworks must be scheduled separately from the superior network.
  • B. Maintenance orders can be defined as subnetworks.
  • C. The scheduling type of a subnetwork is always copied from the superior network.
  • D. A subnetwork cannot be defined for a superior subnetwork.

Answer: B

 

NEW QUESTION 19
Which sets of dates can be used to schedule networks? Note: There are 2 correct Answers to this question.

  • A. Planned dates
  • B. Baseline dates
  • C. Forecast dates
  • D. Basic dates

Answer: C,D

 

NEW QUESTION 20
Which of the following business processes do NOT lead to the booking of actual costs to an object?
Note: There are 2 correct Answers to this question.

  • A. Goods receipt into unvaluated project stock
  • B. Goods receipt of a non-stock item
  • C. Goods receipt into valuated project stock
  • D. Recording of external services in the service entry sheet

Answer: A,D

 

NEW QUESTION 21
You have assigned a material to a network activity and want to determine the requirement date related to this activity. What set of dates do you have to maintain?

  • A. Basic dates of the network activity
  • B. Forecast dates of the WBS
  • C. Basic dates of the WBS
  • D. Actual dates of the network activity

Answer: A

 

NEW QUESTION 22
Where do you maintain the length of the project ID?

  • A. Project profile
  • B. Project type
  • C. Special characters
  • D. Project coding mask

Answer: D

 

NEW QUESTION 23
Which of the following actions can transfer actual costs for external processing? Note: There are 2 correct Answers to this question.

  • A. Saving a goods receipt
  • B. Saving a purchase order
  • C. Saving a supplier invoice
  • D. Saving a service entry sheet

Answer: A,D

 

NEW QUESTION 24
Which statements describe planned and actual revenue for WBS elements? Note: There are 2 correct Answers to this question.

  • A. Planned revenue can be transferred from a sales quotation.
  • B. Planned revenue requires a sales order assigned to a WBS element.
  • C. Actual revenue is posted via a billing plan assigned to a WBS element.
  • D. Actual revenue is posted via a billing document created from a sales order

Answer: A,D

 

NEW QUESTION 25
Which of the following factors influence the scheduling of internal processing activities? Note: There are
3 correct Answers to this question.

  • A. The factory calendar in the work center used for the internal processing activity
  • B. The relationships between activity elements
  • C. An activated Scheduling indicator in the control key of the internal processing activity
  • D. Whether the work for the internal activity is greater than its duration
  • E. The unit (for example, hour, day) of the field Normal Duration field of the activity

Answer: A,B,C

 

NEW QUESTION 26
How can you grant individual authorization for WBS elements and networks?

  • A. Define a user status to lock the business transaction Update Project.
  • B. Set the system status to "Lock Master Data".
  • C. Activate access control lists (ACL) for the project profile and the network profile.
  • D. Activate access control lists (ACL) for the user master record.

Answer: C

 

NEW QUESTION 27
You want to establish costing for WBS. Costing should be easy to use and should not refer to cost elements. What method for costing do you use?

  • A. Easy Cost Planning (ECP) for WBS
  • B. Unit costing for WBS
  • C. Planning of overall values
  • D. Detailed planning for WBS

Answer: C

 

NEW QUESTION 28
What is the reason for assigning billing plans in customer projects?

  • A. Billing plans enable the billing process to be carried out.
  • B. Billing plans are prerequisites for quotation creation.
  • C. Billing plans are used for revenue planning.
  • D. Billing plans are copied automatically to the sales order item.

Answer: A

 

NEW QUESTION 29
You have created an internally-processed network activity, and assigned a work center and the work.
After saving, you discover that no planned costs are displayed in the cost element report for the activity.
What could be the reason? Note: There are 3 correct Answers to this question.

  • A. The activity output price for the activity type and cost center assigned to the work center is not maintained.
  • B. The duration is missing in the activity.
  • C. The formula for costing in the work center is incorrect.
  • D. The Determine Costs indicator in the network header rules out planned cost calculation.
  • E. Integrated planning for the network is active.

Answer: A,B,D

 

NEW QUESTION 30
How are earliest dates and latest dates of activities scheduled?

  • A. Earliest dates are scheduled by backward scheduling, and latest dates by copying the earliest dates.
  • B. Earliest dates are scheduled by forward scheduling, and latest dates by backward scheduling.
  • C. Earliest dates and latest dates are scheduled by forward scheduling.
  • D. Earliest dates are scheduled by backward scheduling, and latest dates by forward scheduling.

Answer: B

 

NEW QUESTION 31
How can you confirm the working hours of different work centers for a single activity?

  • A. Create multiple confirmations for the activity and use the appropriate work center for each confirmation.
  • B. Assign multiple work centers to the activity.
  • C. Enter multiple work centers within a single confirmation.
  • D. Enter direct activity allocation assigning multiple work centers.

Answer: D

 

NEW QUESTION 32
When you create a service activity in your network, what data can be entered? Note: There are 3 correct Answers to this question.

  • A. Overall limit (maximum value of all unplanned services)
  • B. Service purchase order number
  • C. Service specification
  • D. Material master within service specification
  • E. Vendor

Answer: A,C,E

 

NEW QUESTION 33
Which report can use user-specific layouts?

  • A. Cost element report
  • B. Enhanced individual overview
  • C. Line item report
  • D. Hierarchical report

Answer: C

 

NEW QUESTION 34
Your customer has created networks with internal activities and generated capacity requirements. Now, they want to analyze the capacity requirements of their project. Which report do you recommend?

  • A. None
  • B. Individual overview capacity requirements
  • C. Capacity load work center view
  • D. Structure overview
  • E. Extended capacity evaluation

Answer: B

 

NEW QUESTION 35
Float time is calculated during scheduling. Which of the following statements about float time are correct? Note: There are 3 correct Answers to this question.

  • A. By default, critical activities have a float time, which is less than or equal to zero.
  • B. The float time of WBS elements is calculated by extrapolation.
  • C. The maximum size of a free float is as large as the total float of an activity.
  • D. Activities with the time constraint "Must start on" always have a negative float time.
  • E. Float time can be negative.

Answer: A,D,E

 

NEW QUESTION 36
Where do you control whether a project stock is managed as valuated or non-valuated project stock?

  • A. In the material master
  • B. In the network activity
  • C. In the project definition
  • D. In the WBS element

Answer: C

 

NEW QUESTION 37
......