NEW QUESTION 54
Which options do you have to plan both quant ties and capacities during line loading in repetitive manufacturing? Note: There are 2 correct answers to this question.
- A. Run PP/DS heuristics for repetitive manufacturing.
- B. Run MRP with quota arrangement.
- C. Run MRP with automatic selection of production version.
- D. Assign planned orders manual lying the planning table.
Answer: A,B
NEW QUESTION 55
You have maintained the parameters for simple discontinuation the material master of a component. Which business process will be affected if the available stock is zero and the discontinuation date is in the past?
- A. Production order release
- B. Kanban
- C. Back flushing
- D. Material requirements planning
Answer: D
NEW QUESTION 56
How Is the bill of material (BOM) exploded when you use a BOM explosion number?
Please choose the correct answer.
Response:
- A. With respect to a common key date for product and each assembly
- B. With respect to a defined separate change status for product and each assembly
- C. With respect to defined separate key dates for product and each assembly
- D. With respect to a common change status for product and each assembly
Answer: C
NEW QUESTION 57
Which bill of material (BOM) categories can you define in SAP S/4HANA? Note: There are 2 correct answers to this question.
- A. Work Center BOM
- B. Sales Order BOM
- C. Functional Location BOM
- D. Class BOM
Answer: B,C
NEW QUESTION 58
In your plant, MRP is activated. Which options do you have to exclude a material from the MRP run? Note:
There are 2 correct answers to this question.
- A. Use a specific material group
- B. Use a specific MRP type.
- C. Use a specific material status.
- D. Use a specific MRP controller.
Answer: B,D
NEW QUESTION 59
What could be the reason for multiple commitment of individual capacities, where several operations have the same scheduled dates on a resource after capacity planning? Note: There are 2 correct answers to this question.
- A. The planning strategy is infinite.
- B. The work center has several individual capacities.
- C. The Change Planning Direct on indicator is set.
- D. Alternative resources are fully occupied.
Answer: A,B
NEW QUESTION 60
What are the consequences when you assign a planned order to a production line manually, using the planning table in repetitive manufacturing?
- A. The planned order is converted to a production order.
- B. The planned order generates capacity requirements.
- C. The planned order's component availability is checked
- D. The planned order's components are copied from the picking list.
Answer: B
NEW QUESTION 61
What steps are possible in a PP/DS production planning run?
There are 3 correct answers to this question.
Response:
- A. Heuristics
- B. Backorder processing
- C. Demand consumption
- D. Detailed scheduling functions
- E. Optimization
Answer: A,D,E
NEW QUESTION 62
Which material-specific information can be transferred to a transportation lane in PP/DS?
There are 3 correct answers to this question.
Response:
- A. Production versions
- B. Outline agreement
- C. Purchasing info records
- D. Special procurement keys
- E. Quota arrangements
Answer: B,C,D
NEW QUESTION 63
Which of the following functions can be performed when the production order has the status "Created" (CRTD)?
Please choose the correct answer.
Response:
- A. A user can schedule a background job to release production orders (transaction COOIS).
- B. A user trigger printing of shop floor paper manually (transaction CO02).
- C. A user trigger material availability check via mass processing (transaction COHV)
- D. A user can trigger material staging via mass processing (transaction COHV).
Answer: B
NEW QUESTION 64
The procurement type of your material is set to "E" for In-house production. Which of the following is valid to determine a source of supply in SAP S/4HANA?
Please choose the correct answer.
Response:
- A. Selection Method
- B. Purchasing Info Record
- C. Contract
- D. Production Version
Answer: D
NEW QUESTION 65
You have a scheduling agreement with a vendor. You want classic MRP to automatically create schedule lines in case of material shortage. What must you do? Note: There are 2 correct answers to this question.
- A. Add the agreement to the source list and mark it for MRP relevance.
- B. Add the agreement to the quota arrangement and mark it for MRP relevance.
- C. Set the creation indicator for delivery schedule lines on the initial screen of the MRP run.
- D. Set the creation indicator for purchase requisitions on the initial screen of the MRP run.
Answer: A,C
NEW QUESTION 66
You want to create a production order from a planned order. What methods could you use? Note: There are 2 correct answers to this question.
- A. Partial conversion
- B. Order release
- C. Individual conversion
- D. Full conversion
Answer: A,D
NEW QUESTION 67
Which material master setting is required to use the repetitive planning table for production with production orders?
Please choose the correct answer.
Response:
- A. At least one valid production version must exist on the MRP4 view
- B. The Selection Method must be set to "2 Selection by production version".
- C. An overall profile be assigned on the Work Scheduling view
- D. A repetitive manufacturing profile must be assigned on the MRP4 view
Answer: D
NEW QUESTION 68
A planner wants to interactively resolve an overload situation on a resource using advanced planning tools without any automatic rescheduling activity by the system.
Which combination of settings for resource and detailed scheduling strategy are required to receive related alerts?
Response:
- A. Infinite resource and infinite strategy
- B. Infinite resource and finite strategy
- C. Finite resource and infinite strategy
- D. Finite resource and finite strategy
Answer: D
NEW QUESTION 69
......