Unique Top-selling C_TS422_1909 Exams - New 2021 SAP Pratice Exam [Q54-Q69]

Share

Unique Top-selling C_TS422_1909 Exams - New 2021 SAP  Pratice Exam

SAP Certified Application Associate Dumps C_TS422_1909 Exam for Full Questions - Exam Study Guide

NEW QUESTION 54
Which options do you have to plan both quant ties and capacities during line loading in repetitive manufacturing? Note: There are 2 correct answers to this question.

  • A. Run PP/DS heuristics for repetitive manufacturing.
  • B. Run MRP with quota arrangement.
  • C. Run MRP with automatic selection of production version.
  • D. Assign planned orders manual lying the planning table.

Answer: A,B

 

NEW QUESTION 55
You have maintained the parameters for simple discontinuation the material master of a component. Which business process will be affected if the available stock is zero and the discontinuation date is in the past?

  • A. Production order release
  • B. Kanban
  • C. Back flushing
  • D. Material requirements planning

Answer: D

 

NEW QUESTION 56
How Is the bill of material (BOM) exploded when you use a BOM explosion number?
Please choose the correct answer.
Response:

  • A. With respect to a common key date for product and each assembly
  • B. With respect to a defined separate change status for product and each assembly
  • C. With respect to defined separate key dates for product and each assembly
  • D. With respect to a common change status for product and each assembly

Answer: C

 

NEW QUESTION 57
Which bill of material (BOM) categories can you define in SAP S/4HANA? Note: There are 2 correct answers to this question.

  • A. Work Center BOM
  • B. Sales Order BOM
  • C. Functional Location BOM
  • D. Class BOM

Answer: B,C

 

NEW QUESTION 58
In your plant, MRP is activated. Which options do you have to exclude a material from the MRP run? Note:
There are 2 correct answers to this question.

  • A. Use a specific material group
  • B. Use a specific MRP type.
  • C. Use a specific material status.
  • D. Use a specific MRP controller.

Answer: B,D

 

NEW QUESTION 59
What could be the reason for multiple commitment of individual capacities, where several operations have the same scheduled dates on a resource after capacity planning? Note: There are 2 correct answers to this question.

  • A. The planning strategy is infinite.
  • B. The work center has several individual capacities.
  • C. The Change Planning Direct on indicator is set.
  • D. Alternative resources are fully occupied.

Answer: A,B

 

NEW QUESTION 60
What are the consequences when you assign a planned order to a production line manually, using the planning table in repetitive manufacturing?

  • A. The planned order is converted to a production order.
  • B. The planned order generates capacity requirements.
  • C. The planned order's component availability is checked
  • D. The planned order's components are copied from the picking list.

Answer: B

 

NEW QUESTION 61
What steps are possible in a PP/DS production planning run?
There are 3 correct answers to this question.
Response:

  • A. Heuristics
  • B. Backorder processing
  • C. Demand consumption
  • D. Detailed scheduling functions
  • E. Optimization

Answer: A,D,E

 

NEW QUESTION 62
Which material-specific information can be transferred to a transportation lane in PP/DS?
There are 3 correct answers to this question.
Response:

  • A. Production versions
  • B. Outline agreement
  • C. Purchasing info records
  • D. Special procurement keys
  • E. Quota arrangements

Answer: B,C,D

 

NEW QUESTION 63
Which of the following functions can be performed when the production order has the status "Created" (CRTD)?
Please choose the correct answer.
Response:

  • A. A user can schedule a background job to release production orders (transaction COOIS).
  • B. A user trigger printing of shop floor paper manually (transaction CO02).
  • C. A user trigger material availability check via mass processing (transaction COHV)
  • D. A user can trigger material staging via mass processing (transaction COHV).

Answer: B

 

NEW QUESTION 64
The procurement type of your material is set to "E" for In-house production. Which of the following is valid to determine a source of supply in SAP S/4HANA?
Please choose the correct answer.
Response:

  • A. Selection Method
  • B. Purchasing Info Record
  • C. Contract
  • D. Production Version

Answer: D

 

NEW QUESTION 65
You have a scheduling agreement with a vendor. You want classic MRP to automatically create schedule lines in case of material shortage. What must you do? Note: There are 2 correct answers to this question.

  • A. Add the agreement to the source list and mark it for MRP relevance.
  • B. Add the agreement to the quota arrangement and mark it for MRP relevance.
  • C. Set the creation indicator for delivery schedule lines on the initial screen of the MRP run.
  • D. Set the creation indicator for purchase requisitions on the initial screen of the MRP run.

Answer: A,C

 

NEW QUESTION 66
You want to create a production order from a planned order. What methods could you use? Note: There are 2 correct answers to this question.

  • A. Partial conversion
  • B. Order release
  • C. Individual conversion
  • D. Full conversion

Answer: A,D

 

NEW QUESTION 67
Which material master setting is required to use the repetitive planning table for production with production orders?
Please choose the correct answer.
Response:

  • A. At least one valid production version must exist on the MRP4 view
  • B. The Selection Method must be set to "2 Selection by production version".
  • C. An overall profile be assigned on the Work Scheduling view
  • D. A repetitive manufacturing profile must be assigned on the MRP4 view

Answer: D

 

NEW QUESTION 68
A planner wants to interactively resolve an overload situation on a resource using advanced planning tools without any automatic rescheduling activity by the system.
Which combination of settings for resource and detailed scheduling strategy are required to receive related alerts?
Response:

  • A. Infinite resource and infinite strategy
  • B. Infinite resource and finite strategy
  • C. Finite resource and infinite strategy
  • D. Finite resource and finite strategy

Answer: D

 

NEW QUESTION 69
......

Best way to practice test for SAP C_TS422_1909: https://www.actualvce.com/SAP/C_TS422_1909-valid-vce-dumps.html